ISLAMABAD, Jul 19 1999 (IPS) - Following the confirmation by China of an accident at the Qinshan nuclear reactor last year, Pakistani scientists are demanding that their government allow an independent assessment of Chashma, a copy of the Chinese reactor.

The state-run Pakistan Atomic Energy Commission (PAEC) has been tightlipped about the accident at Chashma’s prototype and seems to be going ahead with the commissioning of the 300 MW Chashma power plant under construction on the left bank of the Indus River in Mianwali district, 170 km from Islamabad.

“The Qinshan accident highlights the risks that the PAEC is willing to run,” observes Zia Mian, a Pakistani physicist at Princeton University on e-mail from the United States.

Work on the country’s biggest nuclear power plant was commenced in 1992 after Pakistan and China signed an agreement in 1989. Chashma, its critics say, has inherent design problems like its prototype which has had a history of problems and began operations two years behind schedule in 1991 instead of 1989.

Chashma will be Pakistan’s second nuclear power plant, the first is in Karachi. Chashma takes its cooling waters from the Chashma-Jhelum link canal and discharges it into the Indus River.

Mian fears that some of Pakistan’s biggest cities would be at risk in case of an accident. “A major accident could release radioactivity that would contaminate some of the most heavily populated and farmed areas of Pakistan.

“Within 220 kms lie some of the major cities of the country – to the north is Peshawar, to the northeast Rawalpindi and Islamabad, further east is Lahore, and to the south Multan. A typical wind would carry radiation to any of these cities within 12 hours of an accident,” he said.

Mian warns, “This possibility, no matter how small, makes it important there be careful scrutiny of what is happening at the Chinese prototype and at Chashma.”

Endorsing Zia’s stand is Isa Daudpota, a physicist-turned- peace activist, who wants the government to set up an independent body to assess Chashma with a view to ensuring that matters of public safety have been given due consideration in the construction of the nuclear power plant.

“A commission of scientists and representatives from public environmental groups and reputed NGOs should be asked to carry out an independent assessment,” demands Daudpota.

In fact, what Daudpota and many leading non-governmental organisations (NGOs) prescribe is an independent assessment and the monitoring of all nuclear-related facilities — also a requirement under the Convention of Nuclear Safety which Pakistan has signed.

At present, nuclear safety issues are handled by a Nuclear Regulatory Board, which is housed by the PAEC. In fact, the PAEC chairman heads the regulatory board and most of the board’s members are government officials.

“It is impossible for the Board to be independent and ensure that safety issues are given the highest priority. How could the PAEC keep an independent check on its own actions,” said a paper published by an alliance of the country’s leading NGOs, Advocacy Development Network, following the nuclear tests last year.

The Network had demanded clear laws on radiation protection, radioactive waste management, safe transportation of radioactive materials, emergency assistance and planning in the case of accidents and physical protection of nuclear materials.

Environmentalists say the government has not made public an impact assessment report, which was a constitutional requirement under the 1983 Pakistan Environmental Protection Ordinance, now replaced by the Pakistan Environmental Protection Act.

Some even suspect that it was not even done. “Does this law not apply to PAEC? What does Pakistan’s national Environmental Protection Agency have to say about this? What does the provincial EPA have to say?” questions Zia Mian.

However, the officials in the Pakistan Environmental Protection Agency (Pak-EPA) are refusing to comment, saying their director-general is attending a conference in Rome, Italy.

Being built at an estimated cost of around 600 million dollars, Chashma will add only 300 MW to the already installed capacity of 16,752 MW in Pakistan or around 1.8 percent of the existing power generation capacity.

“Pakistan does not desperately need the electricity. The risks with Chashma are great. To take such risks requires powerful reasons. The motivations for the Chashma plant hardly

seem to warrant it,” Zia Mian says.

A former scientist at PAEC has no doubts of the safety of the reactor, and says the government should allow independent scientists to clear the project. “If inspectors from the International Atomic Energy Agency can inspect the plant, why can’t the government allow local scientists …,” he says.

He argues that since Chashma is China’s first nuclear power reactor export, “they would do everything possible (to cut risk) as they have a lot at stake”.

 