Headlines

ENERGY-PAKISTAN: Like Dams, Nuke Plants Need Scrutiny – Activists

Muddassir Rizvi

ISLAMABAD, Oct 23 2003 (IPS) - Pakistan is all set to build its third nuclear power plant, but this has stirred little opposition in a country still embroiled in a debate over plans to build big hydroelectric dams and water reservoirs in the next five years.

Pakistan is all set to build its third nuclear power plant, but this has stirred little opposition in a country still embroiled in a debate over plans to build big hydroelectric dams and water reservoirs in the next five years.

For the last year, proponents of nuclear energy at the state-run Pakistan Atomic Energy Commission (PAEC) have been pointing to the possibility of constructing two more nuclear power plants.

But it was only in October that the Executive Committee of National Economic Council (ECNEC), the highest decision-making body in Pakistan, announced a generous allocation of around 740 million U.S. dollars for the Chashma Nuclear Power Project-Unit-II.

"The project is scheduled to be completed by 2010 and will be an important step in the direction of energy security and self-reliance. Almost half of the project cost will be raised in foreign exchange," a spokesman for the Ministry of Finance said in an interview with IPS. China is providing financial and technical support for the project.

The announcement of a new nuclear power plant came less than a month after Pakistan President Gen Pervez Musharraf unveiled his water policy in a televised address to the nation in September.

Focusing on the issue of water scarcity in the coming years, Musharraf emphasised the need for the construction of big dams and water reservoirs along the Indus River, the water lifeline of Pakistan, whose economic mainstay is agriculture.

Musharraf’s address highlighting the government’s plan to build controversial dams at Kalabagh in northern Punjab and Bhasha, tucked in the mountainous Northern Areas, stirred a storm in the country.

People in the southern Sindh province say the Kalabagh Dam would take away their share of Indus waters and siphon it off to irrigate the lands in politically powerful Punjab province.

Similarly, Pashtun nationalist parties in the North West Frontier Province say that the dam would cause waterlogging in many districts, causing massive displacement and unemployment. The elected assemblies of the two provinces have also unanimously rejected the dam at several occasions in the past.

The debate over big dams also consumed the attention of civil society organisations working on water issues, prompting many to start advocacy campaigns for water conservation, small dams and micro-hydroelectric projects as an alternative to big dams that displace communities, disrupt livelihoods and the environment.

Not many took note of Pakistan’s plans for nuclear power plants, but activists now say they must also be followed just as closely. "There is very little information available about the government’s nuclear-related projects. The whole issue continues to be shrouded in secrecy, but the government’s pro-nuclear energy tilt will certainly lead to nuclearisation," says Khadim Hussain, who heads the advocacy section in the non-government group Action Aid in Pakistan.

It was against this backdrop and in complete secrecy that the government quietly allocated funds for Chashma-II earlier in October, without much media publicity.

The government did not even seek a parliamentary approval for one of the biggest infrastructure projects in the country that involved a huge cost.

"The nuclear issue is out of bounds for parliament as well as the government. The decisions are made by the military, and the government is just told what to do," commented an apparently disgruntled legislator with the ruling Pakistan Muslim League party.

"I am not sure if we could even discuss this issue in the parliament, as it is a matter of national security and only and only the military and its generals have the mandate to deliberate on such issues," said the legislator, who asked not to be named.

A few years ago, the chairman of PAEC had refused to answer probing questions from the parliamentary public accountability committee, saying he was not answerable to the parliament.

Given the lesser attention paid to nuclear issues by both politicians and civil society, the government has met little resistance in pursuing a nuclear course for energy generation.

Located five hours’ drive south-west of Islamabad near the town of Mianwali in the Punjab province along the Indus, Chashma-II will have a gross power generation capacity of 325 megawatts.

Apart from Chasma I, there is also a plant in the southern port city of Karachi. Another research reactor is located near the federal capital.

Pakistan’s government says that it is investing in nuclear energy in order to bring up its share in the country’s total power generation to 10 percent. Another nuclear power plant in Karachi, KANUPP-II, is also coming up.

Currently, Pakistan has 18,000 megawatts of electric generating capacity. Thermal plants using oil, natural gas, and coal account for about 68 percent of this capacity. Hydroelectric power makes up 28 percent and nuclear plants, 2.6 percent.

PAEC officials say that while nuclear energy may involve greater building costs, the production costs are still far less than any other mode of energy generation.

However, some environmentalists and independent nuclear scientists disagree, saying that the government is underplaying the costs involved in meeting the internationally accepted safety standards, production, handling and transportation of nuclear fuel and disposal of nuclear waste.

"There needs to be a public debate over the economic and environmental pros and cons of nuclear energy. The government must give up its policy of secrecy," said A H Nayyar, a physicist and an anti-nuclear activist.

Some green groups have previously expressed concern at the location of power plants at Chashma, which, they say, lies in an earthquake zone.

"Between 1973 and 1999, there were 24 earthquakes with an epicentre within 100 kilometres of the reactor site, and five earthquakes within 40 kilometres,”said one such study released before the commissioning of Chashma-I in 2000.

A study conducted at Chashma by a leading earthquake research centre, the Lamont-Doherty Geological Observatory of Columbia University in New York, the United States, reported that in a six-month period, 19 earthquakes occurred within 50 km of the Chashma site, the nearest at a distance of less than 5 km.

To sceptics of nuclear power here, this proves that the Chashma reactor is prone to accidents due to earthquakes every now and then.

An accident, green groups say, would affect the waters of the Indus, which is the only source of drinking and irrigation water for Sindh province.

 
Republish | | Print |

Related Tags

Asia-Pacific, Development & Aid, Environment, Headlines

ENERGY-PAKISTAN: Like Dams, Nuke Plants Need Scrutiny – Activists

Muddassir Rizvi

ISLAMABAD, Oct 23 2003 (IPS) - Pakistan is all set to build its third nuclear power plant, but this has stirred little opposition in a country still embroiled in a debate over plans to build big hydroelectric dams and water reservoirs in the next five years.
(more…)

 
Republish | | Print |

Related Tags