- “Water is life…” runs a popular jingle from a radio advertisement promoting the work of the National Water Commission in this Caribbean island.
But recently there are many people, especially in the tourism resort town of Negril in the western end of the island, who are complaining that if they are to take the jingle literally they would at this point be lifeless as they have a difficult time accessing the commodity.
“We hardly get any water at all. We are at the end of the line and we only get water after everywhere else is served, including the big hotels on Norman Manley Boulevard,” says Jasmine Thomas who lives in West End area of Negril and who operates a small craft stall outside her house.
As a result Thomas is forced to store water in big drums whenever it comes through the pipes. “I leave the bathroom tap on, and about once a week I will wake up to the sound of water coming through at about 3:00 a.m.,” says Thomas. “That water will last for two hours and that’s the time I use to fill up all my drums.”
She says she has come to accept the situation and does not believe the government has the will to improve the water supply, despite a recent announcement that the authorities plan to do just that.
According to the government, the project to set the Negril water supply straight, should take between 16 and 18 months. “If possible, we will try to complete this project in even less time,” says Charles Buchanan, the NWC’s Community Relations Officer.
Buchanan says he appreciates the magnitude of the problem which has severely affected the fragile tourism industry and has actually forced a number of, especially, small resorts to close their doors.
The NWC is now able to supply some three million gallons of water per day for the Negril area, and that figure may climb to 3.5 million at peak production times, but the demand stands in the region of 4.5 million gallons a day. “We are now working with a system that just cannot meet the full demand of our customers,” says Buchanan.
Unlike the two other leading resort towns of Montego Bay and Ocho Rios, the village of Negril blossomed into a tourist area faster than the government expected it to. It started out as a fishing village on the western coast and eventually became a refuge for a group of people referred to as “hippie” tourists in the 1960s. After that, the town’s popularity soared and its growth outstripped the existing infrastructure.
From just a few villagers the permanent population now stands at some 10,000 but that figure could triple during the winter tourist season.
The current treatment plant located at Logwwod district on the outskirts of the town was built to provide water mainly to the parish capital of Lucea with a small line leading to the village of Negril to the south. But Negril grew at such a rate that Logwood is now unable to serve both towns adequately.
“When there is major break in the line, it takes days for the water supply to return,” complains Christopher Williams, a small guest house operator in Negril. “A good water supply is critical for a tourist resort and these breaks in the line occur far too often.”
“We have never had a consistent water supply. There are days we are without water and when we do have water the pressure is more often than not too low to be of any use,” says David Morgan, resident of the nearby community of Whitehouse.
Buchanan says he expects the problem to be corrected when the new treatment plant becomes operational.
“This project will provide between a minimum of six million and a maximum of 7.5 million gallons a day, depending of course on the availability of the water supply. Given the projected rate of development in Negril and Lucea, we expect this to serve the needs of the service area up to about 2015,” says Buchanan.
But President of the Negril Chamber of Commerce, Cliff Reynolds, is not as confident.
“We asked the NWC if they were sure that 7.5 million gallons is enough. They are convinced that it is, but we’re not so sure. Based upon practical experience, we don’t think it will totally solve the problem, though it will certainly ease the hardship,” says Reynolds.
Some 14 million dollars has been allocated for financing the project. Of that amount, 11 million dollars will be for engineering services and construction and will be provided by the Japanese government through an Overseas Economic Cooperation Fund (OECF). The remaining three million dollars will be from counterpart funds from the government of Jamaica and will finance land acquisition together with a part of the construction costs.
For residents like Hyacinth Johnson a craft market vendor living in rhw community of Whitehouse, the project should have gotten off the ground a long time ago.
She now gets her water from an NWC watershop in the community which has replaced the public standpipes and is now leased to a private operator.
“Sometimes the prices charged by the watershop are beyond my reach, especially if I have not made much money in the market,” she says.
She buys her water by the bucketful and is upset that the operator is considering increasing the rates. “These people have a monopoly and are seeking to exploit the poor. Water is a necessary function of life, not a commodity,” she says.